MiSpeL: storage and charge points in mixed operation
On 1 October 2026 the Bundesnetzagentur set how storage and bidirectional charge points are settled together with solar power. The ruling has been in force since 21 October 2026. Mixed operation is now possible. The fixed feed-in tariff is outside this. So are AgNeS grid charges. Those are still a draft.
What is settled
The ruling is called MiSpeL, decision 618-25-02. It says which part of the power coming out of storage counts as subsidised generation and which part is grid power that you feed back in.
Adopted on 1 October 2026, published in the Bundesnetzagentur's Official Gazette on 7 October 2026, in force since 21 October 2026. Only from then on can the delineation option and the flat-rate option under § 19 (3b) and (3c) EEG be used. That is what § 100 (34) EEG provides.
It applies to the market premium and direct marketing. Not to the fixed feed-in tariff, not to offtake without payment and not to the tenant-electricity premium. AgNeS (GBK-25-01-1#3) is, as of 5 November 2026, still a draft.
The ruling applies to new and existing installations. Storage and charge points do not have to be recommissioned. Existing solar plants whose market premium is currently based on the monthly market value switch to the annual market value when they use the delineation option. Run that through the numbers before switching.
Delineation option
Anyone can use the delineation option. Volumes are calculated per quarter hour. As a rule you need two meters; in special cases one is enough. That lets a battery mix solar power and grid power and still stay proportionally in direct marketing.
Grid power that is stored and fed back in gets a levy privilege, meaning the CHP levy and the offshore grid levy. For batteries, storage losses count as well, as far as they belong to the re-injection, capped at the arbitrage share. For charge points they do not count.
Calculation runs per calendar month. For the annual final settlement the monthly values are added up to an annual value.
The old separation, the exclusivity option under § 19 (3a) EEG, still exists. MiSpeL does not abolish it. It adds mixed operation. If you stay with exclusivity, you may not store any grid power during the entire calendar year. A single grid draw for charging costs the subsidy for the whole year.
Plant combinations with storage that receive payments from an award under the Innovation Tender Ordinance (InnAusV) are excluded.
Flat-rate option
The flat-rate option is the simpler route for solar plants up to 30 kWp, with a battery or a bidirectional wallbox, at home or in small businesses. Plug-in solar devices do not count towards this limit. Behind the feed-in point, only solar plants, storage and charge points of the same operator may generate power. Usually the meter at the house connection is enough. You do not need to rebuild the meter cabinet.
The law caps the subsidised volume at 500 kWh per kilowatt of solar capacity per year (§ 19 (3c) EEG). Up to that limit, feed-in counts as eligible on a flat-rate basis. Only above a second, higher limit does it count as eligible for netting under the levy privilege. In between lies an indifference band with neither subsidy nor privilege. Netting here is annual.
This option depends on state-aid approval by the European Commission (§ 101 (1) EEG). It can apply at the earliest from the first day of the month following approval. The Bundesnetzagentur has not given a date.
Bidirectional charge points
Bidirectional charge points are included. That means a wallbox through which the vehicle can also feed power back. In the delineation option they are settled together with the storage. In the flat-rate option together with solar plants up to 30 kWp.
Negative prices
In both options the market premium is paid only for quarter hours in which the applicable value is above zero. Whether it drops to zero at negative prices is governed by § 51 EEG, depending on the plant. MiSpeL changes nothing about that. An older plant without that rule keeps its subsidy.
The Bundesnetzagentur writes in its background paper: for feed-in despite negative market prices, the levy privileges and, where the EEG provides for it, the subsidy payments lapse. How the battery runs at negative prices therefore belongs in the marketing contract.
Transition until 30 September 2027
Until 30 September 2027 both options work only if the grid operator and the metering operator agree. They need that time to set up their billing. The flat-rate option also needs EU approval.
What MiSpeL does not cover: the connection
MiSpeL governs settlement. It does not govern the grid connection agreement. If you want to charge the battery from the grid, the connection needs an agreed withdrawal capacity. A connection designed only for the feed-in of a solar plant is not enough.
Whether the grid operator charges a construction cost contribution (Baukostenzuschuss) for the additional withdrawal capacity is set out in its terms. That follows from connection law, not from the ruling. I clarify it before the battery charges from the grid for the first time.
Bundesnetzagentur sources
- Bundesnetzagentur, MiSpeL ruling, operative part with reasoning, decision 618-25-02 of 1 October 2026 (PDF, German)
- Bundesnetzagentur, MiSpeL background paper, 1 October 2026 (PDF)
- Annex 1, delineation options, decision 618-25-02 of 1 October 2026 (PDF)
- Annex 2, flat-rate options, decision 618-25-02 of 1 October 2026 (PDF)
- Official Gazette of the Bundesnetzagentur 19/2026 of 7 October 2026 (PDF, German)
Read next
Status 5 November 2026. Based on the ruling of 1 October 2026 (decision 618-25-02) with operative part, reasoning and annexes 1 and 2, the background paper of the same day and the notice in the Bundesnetzagentur's Official Gazette of 7 October 2026. The German text governs. This is not legal advice.
Frequently asked questions
Since when does MiSpeL apply?
Adopted on 1 October 2026, published in the Official Gazette on 7 October 2026, in force since 21 October 2026. Until 30 September 2027 only with the consent of the grid operator and the metering operator.
Does MiSpeL apply to the fixed feed-in tariff?
No. The ruling covers the market premium and direct marketing. The fixed feed-in tariff, offtake without payment and the tenant-electricity premium are not included.
Does MiSpeL also apply to existing installations?
Yes. The ruling applies to new and existing installations. Storage and charge points do not have to be recommissioned. Existing solar plants switch from the monthly to the annual market value when they use the delineation option.
What is the difference between delineation and flat rate?
The delineation option calculates volumes per quarter hour and is open to everyone. Usually with two meters. The flat-rate option is the simple route for solar plants up to 30 kWp with storage or a bidirectional charge point. Usually one meter at the house connection is enough. It also needs EU state-aid approval.
What applies at negative prices?
The market premium is paid only in quarter hours in which the applicable value is above zero. Whether it drops to zero at negative prices is governed by § 51 EEG, depending on the plant. According to the Bundesnetzagentur's background paper, the levy privileges lapse for feed-in despite negative market prices.
Is my feed-in connection enough to charge the battery from the grid?
As a rule, no. Charging from the grid requires an agreed withdrawal capacity at the connection. Whether a construction cost contribution is due for it is set out in the grid operator's terms. MiSpeL does not govern the connection.
Can I use mixed operation straight away?
Until 30 September 2027 only if the grid operator and the metering operator agree. The flat-rate option also only after EU approval. No date has been set for that.
Does MiSpeL replace grid charges under AgNeS?
No. As of 5 November 2026 AgNeS (GBK-25-01-1#3) is a draft. The consultation ended on 18 September 2026. The Bundesnetzagentur intends to adopt it within calendar year 2026. Under the draft, the 20 years without grid charges remain only with an investment decision before the planned publication on 1 January 2027.