Problem

A single battery serves one market per time window. A cluster can serve several, because different units take different windows. Prequalification and the minimum size remain the hurdle.

What I do

  • I set out the structure: which units should join, which markets are realistic at the minimum size, which points the marketer’s contract must settle.
  • I accompany the choice of marketer.

How it runs

  1. 1FCR, aFRR and mFRR each require a 1 MW minimum bid under Bundesnetzagentur decision BK6-21-042 of 28 April 2022.
  2. 2Prequalification with the transmission operator, proof of controllability and a marketing contract are what turn a pool into a bid.