Co-location and overbuilding: storage on an existing grid connection
Co-location means the battery uses a connection that a PV plant or a consumer already has. Overbuilding means installed capacity sits above the agreed connection capacity, because not everything hits the grid at once.
What is different at an existing point
A new site needs a new request. A battery at an existing point starts with who the connection customer is, which capacity was agreed, and whether the contract allows export, import or both. The point stays. The way it is operated changes.
Metering then becomes the real work. Separating solar generation, grid import and battery operation depends on the meter setup. MiSpeL of 1 October 2026, in force since 21 October 2026, governs mixed operation for the market premium and direct marketing, not the connection contract.
Overbuilding is not an automatic approval
Installed capacity above the agreed connection capacity is only acceptable if the operator allows it and the plant can be limited once that capacity is reached. Whether that is possible at your point is not a general rule on this page.
The same question returns for a construction-cost contribution and a reservation: does the battery trigger expansion, or does it stay inside existing capacity? The operator answers that from the connection rules.
Three ways to run the battery
If the battery charges only renewable power throughout the calendar year, support for the stored power is kept via the exclusivity option (section 19 (3a) EEG). A single grid draw for charging costs it for the year. If the battery mixes solar and grid power, that has worked since 21 October 2026 via the delineation or flat-rate option under MiSpeL. A stand-alone battery with its own connection markets freely, without EEG support and without a shared connection.
The more freedom in marketing, the more metering and control effort. At a shared connection three questions shape the business case: how is the connection capacity split? Is import allowed, or is it a pure feed-in point? And who runs what when the operator limits capacity?
Grid package: grid-neutral storage at an existing connection (bill)
The government bill on the so-called grid package (Bundestag printed paper 21/7866 of 7 September 2026) amends section 17 (2a) of the Energy Industry Act. Sentence 1 already applies today: the connection priority for renewable and CHP plants does not apply against energy storage. Sentence 2 is new: at an existing grid connection point, the operator is no longer to be able to refuse a battery's connection by citing a capacity shortage if the previous maximum withdrawal or feed-in capacity stays unchanged. A flexible connection agreement under section 17 (2b) of the Energy Industry Act or section 8a EEG is a precondition.
The explanatory memorandum calls these grid-neutral batteries in co-location, at renewable plants as well as at charging points or data centres. For a battery at a new point, sentence 2 offers nothing. As of 5 November 2026 this is a bill, not law.
70 percent at the grid connection point: an incentive for storage (bill)
The same bill amends section 8 (1) EEG. For plants connected from 1 January 2027, the right to a grid connection is to exist only with limited active-power feed-in at the grid connection point. For first-segment solar plants, i.e. ground-mounted plants and plants on structures that are neither buildings nor noise barriers: 70 percent of installed capacity. For onshore wind: 280 watts per square metre of rotor area. If several plants share a point, their combined feed-in counts.
The explanatory memorandum says why: fewer feed-in peaks, an incentive for east/west PV together with battery storage in co-location and for low-wind turbines, less grid expansion. The limit is to apply permanently, regardless of congestion. For the battery this means: it absorbs the midday peak above 70 percent and feeds it in later instead of having it curtailed.
The Bundesrat wants to move the cut-off date to 1 January 2030 and to protect plants permitted or applied for by the end of 2026. The federal government is examining both. Anyone connecting a solar park in 2027 should therefore plan the battery now, before the text is final.
EEG 2027: contract for difference and stored power (bill)
Under EU law, new support contracts for wind and solar concluded from 17 July 2027 must be two-way contracts for difference (Article 19d of Regulation (EU) 2019/943). The government bill on the EEG 2027 (Bundestag printed paper 21/7867) implements this with a refinancing contribution (section 21d EEG 2027 draft). If the annual market value is above the applicable value, the operator pays the difference per kilowatt-hour fed in to the network operator. This applies from 100 kW, for plants with an award or a notification under section 20 (2). The bill provides no market value corridor.
Stored power is expressly covered (section 21d (1) sentence 3 EEG 2027 draft). The formula uses the annual market value of the technology, not the revenue of the individual battery (annex 1 no. 4.1). Per kilowatt-hour the contribution is therefore at most the annual market value minus the applicable value. In quarter hours with very low prices it is reduced so that a minimum revenue remains (annex 1 no. 4.2). The operator keeps the extra revenue in the evening compared with the midday peak. Shifting through the battery can therefore still pay off.
At negative spot prices, both the support claim and the payment obligation lapse for those periods (section 51 (1) EEG 2027 draft). Once, until the end of the tenth calendar year after commissioning, the operator can leave support and contribution permanently (section 21e EEG 2027 draft). There is no way back. As of 5 November 2026 this is a government bill; entry into force is planned for 1 January 2027.
Topics that get mixed up
AgNeS, still a draft on 5 November 2026, is about network charges. MiSpeL is about separating supported electricity from grid electricity. The grid package and the EEG 2027, both still bills, are about connection and support. The connection contract is about capacity and the point. Different texts, different responsibilities.
I sort which text is actually slowing your project. I do not build the plant and I do not market it.
In the same context
Status 5 November 2026. Based on section 19 EEG, the MiSpeL ruling of 1 October 2026, the government bills printed paper 21/7866 (grid package) and 21/7867 (EEG 2027) and Article 19d of Regulation (EU) 2019/943. The bills have not been adopted. Not legal advice. The connection contract and the operator’s current conditions prevail.
Common questions
Can a battery simply share the existing PV connection capacity?
Only if the connection contract and the operator allow it. The connection customer, the agreed capacity and the permitted direction come first.
What does overbuilding mean?
Installed capacity is higher than connection capacity. That only works with a limit so that no more is exported or imported than agreed. Whether the operator allows it is case by case.
Does MiSpeL regulate co-location?
MiSpeL of 1 October 2026, in force since 21 October 2026, regulates the split in mixed operation for the market premium and direct marketing. It does not replace the connection contract.
May the operator refuse a battery at an existing connection because of a capacity shortage?
Today it can refuse a connection under section 17 (2) of the Energy Industry Act if it shows that the connection is not possible or not reasonable for operational, economic or technical reasons, including a capacity shortage. The grid package bill (printed paper 21/7866) wants to change that: if the previous maximum withdrawal or feed-in capacity at the point stays the same and a flexible connection agreement is concluded, a capacity shortage is no longer to be a reason for refusal (section 17 (2a) sentence 2 draft). That is a bill.
What does the 70 percent limit mean for new solar parks?
Under the grid package bill, first-segment solar plants connected from 1 January 2027 are to feed in at most 70 percent of their installed capacity at the grid connection point. A battery in co-location can absorb the peak above that. The Bundesrat wants to move the date to 2030; the federal government is examining it.
Does the EEG 2027 refinancing contribution also apply to power from storage?
Yes, under the bill it expressly covers stored power as well (section 21d (1) sentence 3 EEG 2027 draft). The calculation uses the annual market value, not the battery's revenue. As of 5 November 2026 this is a government bill.