Developing a large battery: eight steps to commissioning

A large battery is not a purchase order. Eight steps show up in almost every project. Duration depends on the site. On top comes building law: where the battery may stand. I accompany the order. I do not build the plant.

1. Land and use

Without land that can actually be used there is no site and no counterpart at the network operator. What stands there today, who owns it, and whether demand or generation already has a connection, has to be clear.

2. Grid connection, early

The preliminary enquiry and the formal request belong at the front. Since April 2026 the transmission grid adds the maturity process. On the distribution grid the operator’s rules apply, including a possible reservation and a construction-cost contribution.

3. Revenue model

Before hardware is firmly ordered, it has to be clear which market will carry the time window. A battery stays with one job per window. Balancing energy requires the 1 MW minimum, alone or in a cluster.

4. Permission, depending on the place

Outside built-up areas, batteries have been privileged under conditions since 23 December 2025, under section 35 (1) no. 11 and 12 of the Federal Building Code (BauGB). Whether that holds at the site or a development plan is needed is set out below in the building-law section. Depending on size, height and the federal state, an immission-control procedure may be added. Local planners settle that with the authority.

5. Technology and supply contract

Capacity, energy, warranty and lead time belong in a contract that matches the revenue assumption. A cell that arrives later than the connection offer is valid moves the whole project.

6. Finance and the investment decision

Finance follows the uncertain items: connection, contribution, permission, lead time. Anyone thinking about grandfathering under the AgNeS draft is holding an investment decision against a text that, on 5 November 2026, was not decided.

7. Construction

Building, foundations, fire protection and commissioning tests are done by the firms hired for them. I do not build and I do not run a site as a general contractor.

8. Commissioning and marketing

Commissioning starts registration, the marketing contract and, where required, prequalification. The marketer runs the markets. I close the loop on whether connection, contract and dispatch still fit together.

Building law: two privileges since 23 December 2025

Until the end of 2025 it was unclear in practice whether a battery outside built-up areas fell under section 35 (1) no. 3 BauGB. Its tie to the location was sometimes denied. Since 23 December 2025 the statute names batteries expressly, in number 11 and number 12. This was introduced by article 5 of the act of 22 December 2025 (Federal Law Gazette 2025 I no. 348). On 19 December 2025 the Bundesrat did not call the mediation committee and asked for clarifications in a resolution.

Number 11 covers the battery at a renewable energy plant. A battery is privileged if it stands in a spatial and functional connection with an existing plant using renewable energy. The statute sets no minimum size.

Number 12 covers the battery without its own generation. Three conditions must all be met. At most 200 metres from the plot boundary of a substation from extra-high to high voltage or from high to medium voltage, or of a power plant of 50 MW or more, whether in operation or decommissioned. At least 4 MW rated power. And per municipality, in total no more than 0.5 percent of the municipal area and no more than 50,000 square metres for all batteries permitted under number 12, including ancillary facilities and open space. According to the explanatory memorandum, whichever limit is reached first applies.

For both: public interests must not stand against the project, access must be secured, and the developer undertakes to dismantle the plant after permanent abandonment and remove soil sealing (section 35 (5) sentence 2 BauGB).

What the Fachkommission Städtebau says on number 11

On 18 August 2026 the Fachkommission Städtebau of the conference of building ministers adopted guidance on numbers 11 and 12. It is an administrative view and an interpretation aid for authorities, not a legal norm.

On size, it assumes as the standard case: battery power up to 1:1 and battery capacity up to 1:4, each relative to the plant's rated power. A 10 MW plant therefore carries, in the standard case, a battery of 10 MW and 40 MWh. More is possible in a justified individual case. Whether DC or AC power counts for photovoltaics is left open in the guidance.

There is no fixed distance limit. Direct adjacency is unproblematic. If no suitable land is available there, the explanatory memorandum says the first suitable, somewhat more distant area can suffice. The further away, the more justification the site needs, because the outer area is to be protected as far as possible. Anyone moving away has to show why the adjacent land does not work.

The battery does not have to store green power exclusively. A battery that only charges from the grid, however, does not fall under number 11. As an indicator, the commission names that the battery works to a significant extent with the plant's power. That fits mixed operation under MiSpeL, but it is a separate test.

Existing does not mean the plant must already stand. Battery and plant can be permitted in parallel. The commission then recommends a reservation of revocation in the battery permit in case the plant is missing when the battery is commissioned.

Number 12, order of review and special cases

For number 12, according to the guidance, the plant including ancillary facilities, access roads and open space must lie entirely within the 200 metre radius. The substation may be permitted in parallel but must be admissible on its own. A priority principle applies to the area cap. Anyone who comes late in a municipality may come away empty-handed. Batteries permitted earlier under number 3 or by development plan do not count towards the cap.

My order: number 11 first, if the battery supplements a renewable energy plant. Then number 12. If neither holds, the commission considers recourse to number 3 excluded. In the literature that is disputed. Then land-use planning is needed, as a rule a development plan. Large storage of 50 MW or more can, on application, go through plan approval (section 43 (2) sentence 1 no. 8 EnWG).

In wind energy areas the plan can provide that storage counts as a wind project under section 35 (1) no. 5 BauGB. Conditions are a spatial and functional connection with a wind turbine, a serving function and no requirement for plan approval (section 249 (6a) BauGB). This applies only if the plan provides for it. In acceleration areas, section 6b WindBG eases the procedure if the battery was foreseen when the area was designated.

In unplanned built-up areas section 34 BauGB applies. The battery must fit into its immediate surroundings, and healthy living and working conditions must be preserved. In practice, the type of area and immission control decide.

Outlook: the government bill amending the Federal Building Code (Bundestag printed paper 21/6588 of 22 June 2026) provides that municipalities can designate special building areas outside built-up areas in the land-use plan. Projects there would be admissible without a development plan, and according to the explanatory memorandum this expressly includes power storage (section 5 (5) and section 35 (1a) BauGB draft). That is a bill, not law in force. Whether the Bundestag still changes number 12, for example the radius, is open.

In the same context

Status 5 November 2026. Building law under section 35 BauGB as in force since 23 December 2025 (Federal Law Gazette 2025 I no. 348), with the explanatory memorandum (Bundestag printed paper 21/3101), the guidance of the Fachkommission Städtebau of 18 August 2026 and the government bill, printed paper 21/6588. Accompaniment, not construction and not marketing. Permission is decided by the authority at the site. Not legal advice.

Common questions

Do you build the battery?

No. I accompany the order of land, connection, revenue and contracts. Construction and operation stay with the companies hired for them.

How long do the eight steps take?

I do not name a general span in months. Connection procedures, permission and lead time set the path, and they differ by site.

Does every battery pass all eight steps?

A battery on an existing connection does not skip the reading of the contract, but it does not start from zero. Co-location is a different first question from an empty site.

Is a battery privileged outside built-up areas?

Since 23 December 2025, under conditions. Under section 35 (1) no. 11 BauGB if it spatially and functionally supplements an existing renewable energy plant. Under no. 12 as a stand-alone battery of 4 MW or more, at most 200 metres from a substation or a power plant of 50 MW or more, within an area cap per municipality. If neither holds, a development plan is needed as a rule.

How large may a battery at a solar plant be under number 11?

In its guidance of 18 August 2026 the Fachkommission Städtebau assumes as the standard case: power up to 1:1 and capacity up to 1:4 relative to the plant's rated power. At 10 MW that means up to 10 MW and 40 MWh. More only with justification in the individual case. The guidance is an administrative view, not law.

Service · Market Entry

Germany Market Entry for International Energy Vendors

I guide manufacturers from the US, Asia and Europe into the German energy and storage market. From the first market study through to the first installers.

Germany is a large market for storage, inverters, chargers, heat pumps and energy software. It's also tightly regulated. A good product isn't enough. You need distributors, a connection the grid operator will accept, and a price that holds up against local competition.

I stay with the entry from the first look at the market through to the first installers. I look at it the way a German installer or utility would. Then I tell you whether the product has a place here.

What you get from me

1. Market and competition

I look at the segment, prices, who is already there, how distribution works, and what end customers expect. And where the gap is, in numbers.

2. Price and position

A price that holds up here: list price, dealer discount, the invoice the customer sees. And what actually sets your product apart.

3. Dealers and installers

I talk to installers, project developers, and distributors, and I bring the first pilot customers together.

4. What the rules ask of your product

VDE-AR-N, the notification to the regulator, the market register, metering, GPKE/MaBiS, REMIT. I turn that into requirements for the product and the process.

5. First steps in the market

A start with a few installers, training for partners, a plan for ads and trade shows, service and support. I stay in the work, not only in the concept.

6. The first one to two years

I stay for 12 to 24 months: prices, a wider sales network, rules that change, and a German subsidiary if you need one.

Typical Mandates

  • US and Asian storage manufacturers (residential, C&I, utility-scale)
  • International inverter manufacturers with hybrid and standalone products
  • Energy management software providers (EMS, VPP platforms)
  • EV charger and charging-infrastructure manufacturers
  • Utility-adjacent software and service providers (billing, market communication, customer portals)
  • International energy suppliers with a DACH growth strategy

Frequently Asked Questions

Who is this relevant for?

Manufacturers and providers from the US, Asia and Europe who want to introduce their product or service portfolio into the German market in a structured way – typically storage, inverters, EMS software, EV chargers, utility-adjacent services.

How long does a typical market entry take?

Market study and strategy 8-12 weeks. Operational channel and first pilot installations 6-12 months. Self-sustaining sales with independent growth after 12-24 months.

What sets you apart from a classic strategy consultancy?

I've done the market myself: more than 15 years, over 2,000 PV projects, six utilities, storage at German sites. I look at it the way an installer, a utility, and a customer would. Not only on slides.

Do you work exclusively in a segment?

In a narrow segment, for example home storage of 5 to 15 kWh, I don't work in parallel for direct competitors. In a wider segment, or with a different customer, I can. That's in the contract.

Which regulatory topics typically arise?

The VDE-AR-N series for grid connection, BNetzA notification duties, MaStR registration, MsbG for metering systems, GPKE/MaBiS for market communication, and above certain thresholds also REMIT compliance. For storage additionally electricity-tax rules and § 14a EnWG load flexibility.

Do you also introduce concrete resellers?

Yes – via the existing GPV network in the German energy sector, qualified installers, EPCs, and distributors are addressed and won for pilot projects. Concrete activation follows after defining target segments.