Maturity process: transmission-grid connection since April 2026

Since April 2026, transmission operators sort connection requests by how mature the project is. Reserving capacity takes more than a pin on a map.

What the process is for

Transmission capacity is scarce. A maturity process is meant to separate requests that carry a project from those that only block a point. TenneT and Amprion, among others, describe this publicly. Other transmission operators publish their own rules. There is not one identical national form.

On the distribution grid the same pressure has other names. Individual operators describe a reservation and evidence of planning maturity. Amounts, deadlines and documents sit in their conditions, not in a table on this page.

What projects are usually asked to show

Typical items are a specific site, a rough technical description, a timetable and a credible path to finance. Some operators also ask for evidence that the land is available or for a planning status. I read the current notice of the operator, I do not recite a national checklist.

An early enquiry without those documents is not a mistake. It is only easy to confuse with a reservation. Skipping a stage loses the request, or triggers a security deposit before the project can carry it.

Extra points for co-location

The joint procedure documentation of the four transmission system operators (version 1.1 of 27 April 2026, first cycle) awards extra points for project hybridisation: several projects in co-location at one grid connection point. One point for at least two applicants of one technology category or for two categories, two points for three categories. The categories are withdrawal, storage and generation.

Each participating applicant or category needs at least 100 MW of feed-in or withdrawal capacity. The criterion weighs 10 percent. The joint project is rated by the weakest participating individual application. A battery requested together with generation or load can therefore move up, provided all parts are mature enough.

The government bill on the grid package (printed paper 21/7866) wants to allow the efficient use of grid connection points, in particular by several connection customers, expressly as a criterion for the order (section 17b (1) sentence 3 no. 5 draft). As of 5 November 2026 this is a bill.

What this means for development

The connection belongs at the start, not after the technology and the finance are fixed. Site, mode of operation and co-location with existing generation change which operator is responsible and which process applies.

I accompany that reading. Technical design and construction are not part of the mandate.

In the same context

Status 5 November 2026, based on the processes described publicly since April 2026 and the procedure documentation of the four transmission system operators, version 1.1 of 27 April 2026, for the first cycle. The current notice of the responsible operator prevails. Not legal advice.

Common questions

Does the maturity process start on a fixed date?

Transmission operators have applied a maturity process since April 2026. The exact start and the version are in each operator’s publication. Distribution grids follow their own rules.

Is there one list of maturity levels?

Not in the sense that every level asks for the same documents nationwide. I read the notice of the operator responsible for your point.

Does an existing offer replace the process?

An offer already granted is a different status from a new request. Whether an old statement still holds under today’s process is for the operator to say. It cannot be assumed.

Grid connection for large battery storage, from the request to the offer

For a large battery, the grid connection often decides earlier than the hardware. I sort the preliminary enquiry, the formal request and the connection offer before a reservation or a construction-cost contribution becomes expensive. I do not build the plant and I do not file the request as the network operator.

What should be clear before the first enquiry

Network operators do not ask for a product name. They ask for the site, the voltage level, active and reactive power, whether the battery imports, exports or both, and how it will be operated. Clarifying that after the enquiry produces questions, not a usable answer.

A preliminary enquiry is not a reservation and not a connection offer. It shows whether capacity at that point is even conceivable. Forms and deadlines differ between the transmission grid and the distribution grid, and again from one network area to the next.

From the request to the offer

The usual path runs from the preliminary enquiry through the formal connection request to a reservation and only then to a connection offer. Evidence of project maturity sits in between. Since April 2026, transmission operators, described publicly by TenneT and Amprion among others, use a maturity process for this. Distribution operators have their own conditions.

An offer names capacity, the connection point and usually conditions. It is not a construction contract and not a marketing contract. Whether a construction-cost contribution is then charged, and on what basis, is decided by the responsible operator. There is no national price list on this page.

What the mandate covers

I read the operator’s conditions against your project: site, mode of operation, timetable, and whether the battery stands alone, behind demand or next to generation. The result is a sequence, not a template to file on your own.

Filing with the operator, plant design and construction stay with you and your planners. I advise. I am not a network operator and not an installer.

Common questions

Is a preliminary enquiry enough?

No. It only tests whether capacity is conceivable. Reservation and the connection offer are separate steps with their own evidence. The responsible operator’s conditions say what is required.

Does the maturity process apply to every battery?

The process transmission operators describe from April 2026 applies to requests on the transmission grid. Distribution grids follow the local operator. Site and capacity decide which one you are in.

Do you file the request?

No. I sort the request and say which documents and which order I see. The connecting party files it, not me as a network operator.

How does AgNeS relate to the connection?

AgNeS (case GBK-25-01-1#3) was still a draft determination on 5 November 2026, not a decision. A connection offer and the draft’s grandfathering rules are two different questions.

What does the grid package change for storage at the grid connection?

The government bill (printed paper 21/7866) is meant to help storage at existing grid connection points: if the maximum capacity at the point stays the same and a flexible connection agreement is concluded, a capacity shortage is no longer to be a reason for refusal (section 17 (2a) sentence 2 draft). Transmission system operators are also to be allowed to consider the efficient use of grid connection points, in particular by several connection customers, when setting the order (section 17b (1) sentence 3 no. 5 draft). As of 5 November 2026 this is a bill.

Not legal advice and not an operator’s offer. Conditions, deadlines and costs are those the responsible operator publishes.