FID before the deadline: is your storage project protected?
The AgNeS draft is not a decision. In the draft, protection under section 118 (6) of the Energy Industry Act remains only if the investment decision is taken before the planned publication. This page lists the questions. It does not give the result.
What the draft says, as of 5 November 2026
AgNeS, case GBK-25-01-1#3, was put out for consultation on 6 August 2026. Consultation closed on 18 September 2026. The Bundesnetzagentur still intends to adopt it within calendar year 2026. There was no decision on 5 November 2026. Publication is planned in the draft for 1 January 2027. Until then it is a draft.
In the draft, the 20-year exemption under section 118 (6) no longer covers every commissioning up to 4 August 2029. It asks for a final investment decision before the planned publication and commissioning by 4 August 2029. Proof to the network operator is foreseen by 31 March 2027. The transitional rule for storage is point 17.5 of the draft, the definition of the investment decision is point 2 no. 1.
The 4 August 2029 deadline is in the statute itself, section 118 (6) sentence 1 of the Energy Industry Act. There, the first withdrawal of power for trial operation counts as commissioning of storage (sentence 6). The sentence in the draft that trial operation does not count concerns generation plants (point 17.4), not storage.
What the draft treats as an investment decision
In the draft, binding orders for components covering at least half of the investment volume are enough, if they cannot be unwound without substantial financial loss. The definition looks at orders, not at a grid-connection offer. A decision taken only after publication is supposed to pay a capacity charge from 1 January 2029, even if commissioning is still inside the statutory window.
On substantial financial loss, the reasoning names 25 percent of the investment volume as a level at which it exists in any case (margin no. 500). After the consultation the Bundesnetzagentur clarified: this is not a minimum threshold and it is not in the operative part. A smaller loss can be enough. Settle the individual case with the network operator.
A battery at the connection of a generation plant has a second route. If the plant enjoys grandfathering under the draft, the reasoning extends it to the coupled battery of the same grid user, even if the battery is built later. An extension of the connection capacity for the battery is not covered (margin no. 413).
Whether your orders, contracts and resolutions meet that is not something this page can say. The case is missing, and the text is not decided. A check here means laying the papers against these draft criteria and naming gaps. It does not certify anything.
What the check is not
Not confirmation that protection exists. Not legal advice. Not a statement that publication will in fact happen on 1 January 2027. If the chamber moves the text, the dates move with it.
A reading for a specific project belongs in a mandate. The longer account is on the AgNeS page.
In the same context
The underlying reading is as of 5 November 2026. Based on the AgNeS draft determination GBK-25-01-1#3 of 6 August 2026 with reasoning and the Bundesnetzagentur's procedure page. The draft is not decided. All dates are draft figures. Not legal advice.
Common questions
Has AgNeS been decided?
No. On 5 November 2026, GBK-25-01-1#3 was a draft determination. Consultation had been closed since 18 September 2026. The Bundesnetzagentur intends to decide within calendar year 2026. There was no decision at that point.
By when must the investment decision be taken?
In the draft, before the planned publication on 1 January 2027, which is 31 December 2026 on the calendar, and commissioning by 4 August 2029. Proof is foreseen by 31 March 2027. Those are draft figures, not decided deadlines.
Is the grid-connection offer enough as an FID?
The definition in point 2 no. 1 of the draft looks at binding orders covering at least half of the investment volume, not at the connection offer. Whether your papers meet that is case by case.
Must the loss on withdrawal be at least 25 percent?
No. The 25 percent appear only in the reasoning, as a level at which a substantial loss exists in any case. After the consultation the Bundesnetzagentur clarified that this is not a minimum threshold. The individual case is to be settled with the network operator.
Does trial operation count as commissioning?
For storage, yes. Under section 118 (6) sentence 6 of the Energy Industry Act, the first withdrawal of power for trial operation counts as commissioning. The sentence in the draft that trial operation does not count is in point 17.4 and concerns generation plants.
Do you certify the protection?
No. I lay the papers against the draft and name gaps. A statement that the exemption applies comes only from a decided text, and from the network operator.